Late payment dues Late payment dues

2 years ago

I booked a flat in Aug 2014 and builder agreement got signed in Oct 2015, now the builder is asking money on late payment to Rs 3,50,000. My question is when is to be the builder project started date considered, is it Aug 2014 or Sep 2015. As per agreement possession was to be handed over to me in 36 + 6 months. The project original starting date was May 2014 as per builder registered in Rera website. Now what is the project started date accordingly will be the completion date of builder. Can i claim from the builder about my interest on delayed possession, rent, mental harassment i am going through. Please be noted the extra interest amount the builder is asking is verbally as of now and not giving in mail or in demand letter as he says he sent demand letter for this then i have to pay this and this amount cannot be negotiated further.

Ayantika Mondal @ Prime Legal

Responded 2 years ago

A.Hi,
You have two legal recourses against the builder now. You can file a complaint before the civil judge's court for the recovery of money involved in the deal. Or you may approach the consumer forum and complaint in regard to inordinate delay in handing over possession.
If you find my answer helpful then kindly rate me.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Anik

Responded 2 years ago

View All Answers
A.Hi,
You can opt-out of the whole deal and ask him to return all your deposited money. You may have to serve a legal notice for this and then you may also have to file a suit before the consumer court for deficiency in services by the builder.
f you find my answer helpful then kindly rate me.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Kishan Dutt Kalaskar

Responded 2 years ago

View All Answers
A.Dear Sir,
You need not pay any amount to him as project was delayed abnormally.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Abhimanyu Shandilya

Responded 2 years ago

View All Answers
A.You ask the builder to send him a letter so that you can pay him that amount and once you have the letter then meet up a good consumer layer in your city and file a case against this builder for his wrongdoings and delays. You shall get not only the possession of your flat in time but also compensation for all these sufferings.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Read Related Answers

question iconExtra amount for completion of project
Dear Client, Please consult an accountant for the how to include new additional income and if the can be given the rights of a builder. additionally with the consent of the new person they can be a...
question iconRENTAL AGREEMENT
Dear Sir, Unless it is registered lease the locking period is not valid. You may give two months notice and get back your security deposit.
question iconOne Flat owner not accepting to pay water charges
Dear sir If maintenance is not paid then you have to get issue a legal notice and file a suit for recovery of such arrears of maintenance.
question iconAccess and usage of road near my house
Dear Client, When the second road approaching your house is not mentioned in the land record or registry, it is legally impermissible to use that road. From the query, it is not clear whether these ro...
question iconCan housing Society Charge differential Maintenance from Owner for Rent Flat
Dear Sir, This is the procedure being adopted by many housing societies that they can claim additional maintenance of 5% and not 15%. It has to be resolved among yourself.