Pagdhi house Pagdhi house

5 years ago

I have a house in Mumbai in Pagdhi System that is in a poor condition and the building has only 12 tenants. Now I wish to sell the house because of the poor standard of living and move elsewhere. But the landlord does not allow me to sell the house and is asking me to surrender the house to her. She is only giving 10 lakhs for a house whose market value is 30-35 lakh.
What can be done now?

Kishan Dutt Kalaskar

Responded 5 years ago

View All Answers
A.Dear Sir,
You may ask for redevelopment fot he house. The relevant provisions are as follows
=======================================================================================================
Things you need to know about property redevelopment
With limited availability of open land parcels in Mumbai, major developers are now looking at venturing into the redevelopment space.
Dilapidated buildings on the verge of collapse are a grim reality for thousands of housing societies across Mumbai. Developers, as an incentive to owners of older buildings, offer additional area, money, and the promise of a new flat with a better amenities .
But owners should keep a few things in mind before opting for redevelopment.
What is redevelopment and why is it needed?
Housing redevelopment refers to the process of reconstruction of a residential premise by demolition of the existing structure and construction of a new one as per approvals from the Municipal Corporation of Greater Mumbai (MCGM). It ideally works best when a society is in dire need of extensive repairs but is starved of the necessary funds for it.
Developers, on their part, are also on the lookout for properties with unused development rights where they can build a new and higher structure where the additional storeys can be sold for a tidy profit.
As per the terms of the agreement between the developer and the society in question, existing members of the society receive new flats in the reconstructed building of an area equal to or more than the area of their existing flats. But redevelopment can only take place if 75 percent of the members tender their consent.
Over 20,000 housing societies, 17,000 cessed buildings and over 3,000 Mhada (Maharashtra Housing and Area Development Authority) structures are waiting for redevelopment proposals.
The advantages of redevelopment over repair
According to Redevelop Mumbai, a project management consultant that has handled over 45 redevelopment housing societies in Mumbai, the repair work of a building which is already 25 years old will only increase the life of the building by three to four years. "Structural repair is not economically feasible to take care of seepage, weak walls and foundations, leaking water pipes, etc," Dilip Shah, Senior Counselor and Analyst for Redevelopment of Housing Societies, told Firstpost

With redevelopment, the members get a new building, more space and monetary benefits without spending any money from their own pockets. Shah says the developer can offer extra amenities like a gymnasium, a generous car park, and high-end security systems, among other things.
Disadvantages
However, while redevelopment may be the latest buzz, citizens argue that developers often tear down old colonial mansions to build luxury towers for the rich. And more often than not, it is often haphazard and done without the consent of society members.
Any building that is over 25 years old can go for redevelopment once it is declared dilapidated by an architect. Under the provisions of Development Control Rules it has become easy for developers to get buildings declared dilapidated even when they are not really so. Given the strong politician-builder nexus in the city, it is not difficult to get a building declared dilapidated by a government architect.
The redevelopment process also causes inconvenience to the residents as they will have to look for alternative places to stay in while the builder demolishes the old building and constructs a new one. It usually takes the builder at least 18 to 24 months to complete a project with an extended grace period of six months in case of any adverse eventuality.
Follow the ground rules
1. Redevelopment is usually burdened with bitterness and complaints of high-handedness and corruption against the Managing Committee of the society, which is why society members should always appoint a lawyer before signing a contract with the builder."Builder should be transparent, reliable and trustworthy. The most recommended way to choose a builder is to go by the tendering system," said Shah.
The society should prepare a comparative chart and, after checking the merit, reputation, technical capability, experience, financial status, quality of construction and successful completion of projects, it should select the builder.
2. The contract should clearly mention the obligations of the builder and the society members and the penalty or consequences of any breach of the contract by either of the parties. Once the agreement is accepted in terms of area and corpus fund, it cannot be revised.
"If the carpet area, as documented in the agreement, is not given by the builder, the owner can claim appropriate compensation through a consumer court by filing a complaint against the builder under the counts of Breach of Trust, Cheating, Unfair Trade Practice and Deficiency in Service," Shah said.
3. The housing society should insist on a bank guarantee, which would take care of monetary compensation to ensure the project is not delayed or stopped midway. "The successful bidder has to give a bank guarantee equivalent to 20 percent of the total project cost," according to redevelopmumbai.com.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Read Related Answers

question iconTo landlord - I am staying in this house from 6 years
Dear Client, You can send a legal notice to the landlord and demand to repay the security deposit. In case of inaction from the landlord, you can file a suit under Order 37 of CPC before a jurisdictio...
question iconAddition of Wife Name in new flat sale
Dear Client, An owner who wants to add a co-owner to his property will have to do so by way of creating a new deed altogether mentioning the ratio or portion of the ownership in the property. This new...
question iconReal estate -rera
Dear Client, As the housing project is not registered under the RERA, you have to file a complaint against the real estate company and its directors before the District Consumer Commission under Sec.3...
question iconApartments terrace laws
Dear Client, The rooftops of the Building are also known as an open terrace and a part of the common area useable for all the floor owners of the multistoried building. Legally, a Builder cannot sell...
question iconTenant Eviction - Rental and Sale Agreement Signed but Expired
Dear Client, Neither a rent agreement nor an agreement to sell confer any ownership right to a tenant or a buyer. On the expiry of the rent agreement, you can ask the tenant to vacate the rented premi...