Mumbai Rera Query Mumbai Rera Query

9 months ago

In ongoing rera reconcilation , builder is stating they have 1 year extenion by default from rera due to pandemic.

What value we can ask for compensation of interest on delay possesion:
Agreement value
Registration plus stamp duty

Agreement was based on construction linked plan
Date of Possession on Agreement : 31 Dec 2021
Agreement value paid all : 07 Jan 2021

Is that one year extension valid ? can we confront in any case!

Legal Counsel Vidhikarya

Responded 9 months ago

View All Answers
A.Dear Client,
From the query, it is not clear from which date Builder gets extension for one year, If the extension period expired or ended before the dead line of delivery of possession i.e, 31-12-2021 as per agreement, then the compensation for delay in delivery of possession shall be counted from the date, the extension is ended to the actual delivery date of possession. You also need to verify the statement of Builder that they were granted extension by RERA for pandemic and the effective date of such extension from RERA. For further clarification you need to consult with a consultant dealing RERA dispute.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Read Related Answers

question iconComplaint on Apartment Maintenance issue
Dear Client, Per sq, ft method is extensively used for the calculation of the maintenance charges for the societies/RWA across the country. This system of calculation is used when the sizes of apartm...
question iconQuestion on Buying 10 years old flat with registration on hold
Dear Client , you can not rent / lease or sell your property until you have received complete possession of the property. you have to complete registration process for the same before getting into re...
question iconREGISTRATION OF Apartment owners association under companies act
Dear sir, It is ordinarily registered under specific act which might have been enacted by your state government otherwise consult the sub registrar office.
question iconI am being asked to pay more than my neighbour for Open Car Parking
Dear Client, Firstly, document all your interactions with the builder, including dates, times, and any communication (emails, letters, etc.). This documentation will be crucial if you need to escala...
question iconExtra amount for completion of project
Dear Client, Please consult an accountant for the how to include new additional income and if the can be given the rights of a builder. additionally with the consent of the new person they can be a...