BOCW LICENSE BOCW LICENSE

9 months ago

IS IS NECESSARY TO GET BOCW LICENSE FOR EACH PROJECTS SEPARATELY OR ONCE LICENSE IS ENOUGH. AS IN LICENSE Postal Addr ss/ cati whe in Boeing India Pvt Ltd., No.5B, 56, 57 and
building or other construction work is to be 59, Hi-Tech, Defence and Aerospace, Jala
carried on by the employer IS MENTIONED SPECIFICALLY

Anik

Responded 9 months ago

View All Answers
A.Dear client,

BOCW stands for "Building and Other Construction Workers" (BOCW) welfare license, which is required in India, for certain construction-related activities.

In India, the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996, mandates that any establishment or contractor engaged in building or other construction work where ten or more workers are employed must obtain a BOCW registration and license.

Each project or construction site is typically considered a separate establishment. Therefore, if a company or contractor is involved in multiple projects simultaneously and each project has ten or more workers, they will need to obtain separate BOCW licenses for each of these projects. Each license will have specific details regarding the project location, address, and other relevant information.

It is essential to comply with the BOCW regulations and obtain the necessary licenses for each construction project to avoid any legal complications or penalties. If you are unsure about the specific requirements or regulations in your area, it is advisable to consult with local authorities or legal experts who are familiar with the BOCW laws and procedures applicable to your specific location and project.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Read Related Answers

question iconCommissioner sir force me to do risky work of demolition as contractor
Dear Client, In the prevailing situation, you can escalate your grievance before the higher authorities explaining your constraint or inability to comply with the order of demolition of the building,...
question iconDelay payment
Dear Sir, Better approach Police and get an undated cheque for the said amount with interest etc. If you go to the court on agreement it will be a civil case as such you have to spend lot of money and...
question iconTermination of contract
Dear client, Please verify with the terms and conditions of the contract verify with if the project has been suspended temporarily or permanently. you can send a legal notice to the company for breac...
question iconWest Bengal Tender for Fortified Rice
Dear sir You may challenge negative order either before higher authorities or by approaching civil court or High court.
question iconBreech of Employment Agreement
Dear Client, Here are the responses to your query no.1) What are some legal actions that they can raise? Ans: The company can file a civil suit against you for damages caused by a breach of its policy...