Vidhikarya Logo
Callback Request
Call Back Request
Track Your Request
Track Your Request
+91-7604047602 Legal Blog For Students Free Legal Advice Lawyer Login
Menu
Vidhikarya
arrow_back

How to get compensation from builder under RERA act?


How to get compensation from builder under RERA act?
When there is a default on the part of builder and does not comply with agreement terms then the Home buyer can seek for compensation for defaults of Builder/Developer under sec.18 of Rera Act.

Under sec.18 of the RERA act, If the Builder fails to complete and handover the possession of an apartment, plot or building on an agreed date under the terms of agreement, as the case may be and on such default of the builder the allottee/s have the right either to continue with the project and seek for delay compensation from the builder for the number of days delayed by the builder in handing over the possession of the apartment plot or building. (Handing over means & includes completion and occupancy certificate for the building/project). Or in the alternative to seek for cancellation and refund of the amount with interest at the rate of SBI Highest Marginal rate of lending plus 2% on the amount paid by the allottee/s till the date of payment.

(When the payments are made on different dates the calculation will be from the date of payment and on the amount paid.)

Karnataka Rera Rules, 2017 prescribes that the builder/developer is liable to oblige the order passed under sec.18 within a period of 60 days from the date of order.

Further Rule 25 & 26 prescribes that if the builder/developer has failed to make the payment under sec.18 read with rule 15 &16 of the execution of the order passed by the Adjudicating officer & Real Estate Appellate tribunal shall be executed as per the procedure of law.

If the allottee/s does not intend to withdraw from the project, allottee/s shall be entitled for interest for every month of delay till the date of handing over of possession.

The allottee/s shall be entitled for the above reliefs whenever there is a default of builder may be for the reasons like discontinuance of the business as developer due to suspension or revocation of registration under the act or for any other reasons (Except FORCE MAJEURE EVENTS)

The allottee/s are entitled for compensation in case where the project lan suffers defective land title. Whenever there is a defect in the land title then also the project allottee/s or home buyers in the project are entitled for compensation from the builder/developer of the project.

If the promoter fails to perform his part of obligations under the provisions, rules & regulations of this act or fails to perform his obligations under the terms of agreement entered between the builder/developer & allottee/s then the allottee/s shall be entitled for the relief of compensation.

Sec.18 of RERA act is compensatory in nature & not a penalty imposed on the builder/developer. As a measure of protection an allottee/s can have compensation only from the builder for the defaults.


For seeking the compensation from the builder under this provision of the act, allottee/s will have to file a complaint before the RERA Adjudicating officer as per FORM ‘O’ [See sub-rule (1) of rule 30] APPLICATION TO ADJUDICATING OFFICER- Claim for compensation under section 31 read with section 71. If the allottee/s fails to get the proper & reasoned order from Adjudicating officer under the above mentioned provision. The allottee/s can appeal the order passed by the Adjudicating officer before the RERA Appellate Tribunal as per FORM-R [See sub-rule (2) of rule 33] APPEAL TO APPELLATE TRIBUNAL - Appeal under section 44 of the Act within 60 days from the date of order passed by the Adjudicating officer an seek for the reliefs in appeal.


Sec.18. reads as under -

(1) If the promoter fails to complete or is unable to give possession of an apartment, plot or building,—

(a) in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or

(b) due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act:

Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.

(2) The promoter shall compensate the allottees in case of any loss caused to him due to defective title of the land, on which the project is being developed or has been developed, in the manner as provided under this Act, and the claim for compensation under this subsection shall not be barred by limitation provided under any law for the time being in force.

(3) If the promoter fails to discharge any other obligations imposed on him under this Act or the rules or regulations made thereunder or in accordance with the terms and conditions of the agreement for sale, he shall be liable to pay such compensation to the allottees, in the manner as provided under this Act.


KARNATAKA RERA RULES WITH RESPECT TO SEC.18

RATE OF INTEREST PAYABLE BY PROMOTER AND ALLOTTEE AND TIMELINES FOR REFUND

16. Rate of interest payable by the promoter and the allottee.- The rate of

interest payable by the promoter to the allottee or by the allottee to the promoter, as the case may be, shall be the State Bank of India highest marginal cost of lending rate plus two percent.

17. Timelines for refund.- Any refund of money along with the applicable

interest and compensation, if any, payable by the promoter in terms of the Act or the rules and regulations made there under, shall be payable by the promoter to the allottee within sixty days from the date on which such refund along with applicable interest and compensation, if any, becomes due.

25. Manner of recovery of interest, penalty and compensation.- Subject to

the provisions of sub-section (1) of section 40, the recovery of the amounts due as arrears of land revenue shall be carried out in the manner provided in the Karnataka Land Revenue Act, 1964 and the rules made there under.

26. Manner of implementation of order, direction or decisions of the adjudicating officer, the Authority or the Appellate Tribunal.-

For the purpose of sub-section (2) of section 40, every order passed by the adjudicating officer, regulatory authority or Appellate Tribunal, as the case may be, under the Act or the rules and regulations made thereunder, shall be enforced by the adjudicating officer, regulatory authority or the Appellate Tribunal in the same manner as if it were a decree or order made by the principal civil court in a suit pending therein and it shall be lawful for the adjudicating officer, regulatory authority or Appellate Tribunal, as the case may be, in the event of its inability to execute the order, send such order to the principal civil court, to execute such order either within the local limits of whose jurisdiction the real estate project is located or in the principal civil court within the local limits of whose jurisdiction the person against whom the order is being issued, actually and voluntarily resides, or carries on business, or personally works for gain.

Posted On : June 30, 2020

Written By :
Sharada H v
Sharada H v
D.O.E. : 8/2004
Bangalore |
Consult

Recommended Free Legal Advices
question markinferior quality product delivered, description of product was false in website
Issue them a legal notice and if it is not replied or not complied within 15 days than you can think of filing case in the consumer Court in Bandra if your are located in Mumbai. Thank you. If you have found this answer helpful than provide review and give ***** as appreciation.
question markFound insects in rice bag
File a Consumer complaint in the respective forum. For clarifications please contact. There is a procedure for it. If u want you can proceed further. you should firstly file a consumer complaint and fight the case. Please do fight as it is necessary to punish the cheaters who are making money in the name of Made in Bharat.
question markDefrauded by an astrologer what action can be taken?
Hi, You can hold him guilty under Section 424 of the IPC states that "whoever dishonestly or fraudulently conceals or removes any property of himself or any other person, or dishonestly or fraudulently assists in the concealment or removal thereof, or dishonestly releases any demand or claim to which he is entitled, shall be punished with imprisonment if he does not give back the amount duly. File a compalint at the local police station. Thank you.
question markidea cellular wrong international usage bill & pre-litigation notice
Dear Sir/ Madam, You either wait for the next date of pre-litigation or approach a legal representative for the effective legal procedure since more delay could only worsen the matter. If you find this response useful then please rate me
question markRERA or Consumer Forum where to file the case
What do you mean by have already tried DCDRF, builder always appeals and stays? Whatsoever it is the Builder can appeal only twice to State Forum and National Forum ( rarely to Supreme Court). So, even after appeal if your case is strong you can win over. Stay is in the lower forum as appeal is going on in higher forum so fight the case in higher forum and you shall win over there as well and save time. Starting a fresh case in any forum means going back to square one. Secondly your case might not be entertained by the RERA court unless you withdraw the cases in Consumer forum.
Expert Lawyers in Consumer Protection Real Estate Property
GIRRAJ
D.O.E. : 3/2013
Jaipur
View Full Profile
Nidhi
D.O.E. : 6/2006
Delhi
View Full Profile
ANISH
D.O.E. : 12/2007
Mumbai suburban
View Full Profile
KETKI
D.O.E. : 9/2010
Nagpur
View Full Profile

Please enter the text

Categories

Civil(39)
Family(37)
News(2)
Others(14)
RTI(7)
Sale(4)
Tax(4)
Torts(4)
Will(3)
Writ(1)

Send your queries to

[email protected]
X
Consult Property Lawyers from your City!
Post Your Matter
Post Your Matter to connect with the Lawyer online
Call 7604047602 for any assistance
Symbol for Lawyer
Find Lawyers by Location


Download the Clients App on

Vidhikarya App on Android Platform

Contact Details

7604047602
[email protected]
505-A, Terminus Building,
Newtown, Action Area I,
Kolkata 700156

Download the Lawyers App on

Vidhikarya App on Android Platform

Certified by Startup India, DPIIT

startUpIndia

Payment secured by :

PayUMoney PayPal net banking
visa master maestro
Celebrating 5 years