icon Delay to Complaint in MAHARERA

I purchased flat in Mumbai and RERA completion date was May 2019 but Builder had Money Problem so he requested us to wait. We didn't complain in RERA and trusted the Builder, but now he is asking more

2 Response(s)

9 months ago


A. Dear Client,
Though there is no time limit to file a complaint under the Real estate regulatory authority (RERA). Still, the provisions of the Limitations Act, 1963 is to be adhered to make sure that RERA proves its efficiency when approached in a reasonable time limit following the Limitation Act i.e, within 3 years from the date of cause of action. Delay in filing a complaint against the Promoter/Builder is condoned on appeal if RERA finds reasonable ground behind the delay and considers the m ...ReadMore

Helpful
Helpful
Share
icon cancellation of allotment

allotment can be cancelled without giving notice if there is clause in general terms that if payment is not done within in stipulated time , the allotment will be cancel and reserve money will forfie

1 Response(s)

9 months ago


A. Dear Client,
If a homebuyer, otherwise known as an allottee, fails to make the necessary payments for a continuous period of time as per the payment schedule, the developer is empowered to terminate the agreement and revoke the allotment made to the buyer and can charge interest for delay in payment. The provision of refund here is no different from the general RERA rule i.e. the amount paid to the promoter must be refunded to the homebuyer within a period of 90 days, excluding booking amount a ...ReadMore

Helpful
Helpful
Share
icon Fencing the society by developer

can you tell me if it is legal to start fencing a society by the builder without giving the society IOD or DA

2 Response(s)

9 months ago


A. Dear Client,

From the query, it appears that the housing complex is still under the hand of the Builder or Developer and there exists no registered society to manage the activities of the maintenance of the housing complex. Fencing of Society is a part of the maintenance work which is taken care of either by the Builder/Developer or a registered housing society. On the formation and registration of a registered society, Builder/Developer handed over the maintenance of the housing complex to the ...ReadMore

Helpful
Helpful
Share
icon Legal advise - govt office on rental building

I want to know a govt office on rental building comes under commercial or domestic entity

2 Response(s)

9 months ago


A. Dear Client,

Any revenue generated from rent or lease of any place or building is termed as a commercial complex irrespective of class or nature of activities carried on by the concerned entities and such building or complex is liable for payment of charges at the commercial rate against all the facilities available from the different authorities like Municipal authorities, Electricity authority.

Helpful
Helpful
Share
icon Allotment of land

How do I apply for the allotment of land for ex-servicemen I have served in the IAF as a pilot for 14 yrs in ssc My sevice will b over in dec 30 2023 I want to avail the benefit Pls advice

1 Response(s)

9 months ago


A. Dear client,

1/20th of the available/assignable land in each district is reserved for assignment to Ex-servicemen. Preference is given to the Defence personnel and their dependents for allotment of land under the Housing Scheme viz, Land Acquisition and Development Schemes.

o apply for the allotment of land for ex-servicemen in India after completing 14 years of service, you typically need to follow these steps:

Research: Gather information about the specific state government's policy regardi ...ReadMore

Helpful
Helpful
Share
icon Sale deed registration along with a forced affidavit

I am in the process of buying a residential property on resale from the Seller. Both parties entered into an agreement to Sale after which the SAle Deed was to be executed. 10% of the total property v

1 Response(s)

9 months ago


A. Dear client,
If you are being forced to sign the affidavit, please send a legal notice to the seller. If this does not work out, please approach the Court for the remedy of specific performance of the transaction

Helpful
Helpful
Share
icon Property registration - planning to buy a flat in Kolkata

I am planning to buy a flat in Kolkata. My home loan is already disbursed, and i have already paid my down-payment and stamp duty charges and registration fees. Problem is, My bank said that property

2 Response(s)

9 months ago


A. Dear client,

Since the bank themselves informed that it will take 3 more days to register the property, it was evidently not your intention to miss the date . Therefore, you can explain this nuance to your builder

Helpful
Helpful
Share
icon Self redevelopment

Can a society in Mumbai island city go in for self redevelopment if 100% of society members are willing but 4 out of 8 tenets are not willing to give consent for redevelopment. If yes what is the proc

2 Response(s)

9 months ago


A. Dear Client,
Only resident apartment owners can be eligible for membership in the registered Society which is governed by its Byelaws and regulations. In the query, the word tenants is being applied who are not willing to the redevelopment of Housing Complex. The tenants are not treated as Owners of the apartment/flat, so they are out of the ambit of governing Byelaws of the Society. So, notice is required to be issued asking the consent of the member Owner of the apartment who let out their apa ...ReadMore

Helpful
Helpful
Share
icon Real estate agent harrasing for brokerage

An agent showed me a flat in Hyderabad. I was interested in the flat and kept following up with him to close the deal. The agent told me that owner is asking for too much money and we should drop this

2 Response(s)

9 months ago


A. Dear client,
there is absolutely no need to pay him any brokerage.
Please file a police complaint against broker for criminal intimidation, extortion under section 384 , 506 of IPC

Helpful
Helpful
Share
icon Builder not provided still car parking

I have paid 5 lakhs for still car parking but the receipt is not given by Builder. Only the allotment letter mentioned one still car parking.

2 Response(s)

10 months ago


A. Dear Client,
An allotment letter is also a valid document and forms a part of the Agreement to Sale even if it is left to mention in the agreement and on the issue of the allotment letter by the Builder to you alloting still car parking and on receipt of money for the same if the money is transferred digitally or through documentation, the builder is dutybound to allot you the parking as you are legally entitled for the same; There are two ways to resolve your grievance. 1) to file a complaint ...ReadMore

Helpful
Helpful
Share