I pre-booked flat in Mumbai on 03/04/2014 during that time RERA was not in existence due to which there was no possession date mentioned on the booking form.
Later the registration of the said flat was done on 27/01/2016 ( do not know if RERA existed) in which the date of possession was said to be Aug 2019 however as of 12/11/2020 they have still not provided me the possession. They had additional 6 months of grace period which also ended on Feb 2020 (COVID-19 19 came into effect on March 25, 2020) & The builder finally received an OC in July 2020
1. My registration agreement mentions that we have right to terminate the agreement and ask for compensation and builder will have to pay the penalty on the same. (no specific details mention)
2. The plan of the building was 22 floors however this was later changed to 40 floors adding to the delay.
3. Payment schedule was provided to me with any dates.
4. All the payments have been done from our side till date as per the demand letters but after all this was done on 29th August 2020, Relationship manager from Builder side said that we must pay Rs. 92000/- as interest charges.
5. This interest charges (21%) was communicated to us for 1st time in June 2017, I had provided all the justification and clarification regarding the delays ( NRI owner Delay in Registration process & Home loan approval as they only had agreement with one bank) , Our request was under management review and since then was never communicated back to me. I had emailed builder's relationship manager in April 2018 and again later in December 2018 asking for a resolution, no answer for provided to me from Builder side.
5. Being a well renowned Builder, the Relationship lacked professionalism, also being an NRI, we had no visibility of the payments. (they did not have any online Portal for the customer)
6. None of the Demand letters after June 2107, mention about Interest charges to be paid by us.
7. I requested the Builder to waive off the interest charges as there was no clarity on resolution was provided or communicated to me. This request is rejected.
8. Builder has not done any official communication regarding date of possession in letter or over email.
The builder said they will not pay us any compensation for the losses we have incurred since Aug 2019, As an NRI, we invested in the property to put in on Leasing & we have lost 1 yr and 3 months of monthly rental because of possession delay.
May I kindly request to let me know, how can we ask the Builder to pay us compensation and not terminate our contract?
How can Builder asking me to pay for interest charges, when they never provided me correct justification or clarification? and why in 2020 when all the payments were done with minimum delay
Am I covered under RERA Act? I already official complaint via Maha RERA online platform? what will be the delay in processing?
I look forward to your answers
Thanks in Advanced
Mr. Kelkar

Kishan Dutt Kalaskar

Responded 3 years ago

View All Answers
A.Dear Sir,
Documents to be shared to get exact legal advise however you can file case before RERA and pursue the same.

Rate me Five Star*
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Ayantika Mondal @ Prime Legal

Responded 3 years ago

A.Hello,
RERA is not a law with retrospective effect since it covers all projects, which have not got completion certificate by May 1, 2017. Though there are no such delay in the proceedings under MAHARERA, but in case, this happens you can send a legal notice to the builder and file a case against him
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Anik

Responded 3 years ago

View All Answers
A.Hi,
Usually there is no delay in the proceedings under Maha Rera, but, if it is happening you may send a legal notice and than file a case against the builder. Also, RERA is not a law with retrospective effect since it covers all projects, which have not got completion certificate by May 1, 2017.
Helpful
Helpful
Share

Post Your Matter Post Your Matter

Talk to a Lawyer Talk to a Lawyer

Ask a question Ask a question

Vidhi Samaadhaan Vidhi Samaadhaan

Read Related Answers

question iconInheritance Rights Dispute Over Mothers Property in Bengaluru
Dear Client, A property when left by the deceased owner intestate i.e, without any will, is devolved upon the surviving legal heirs in equal share following the law of inheritance/succession. After t...
question iconEWS Certificate
Dear Client, The death certificate of a deceased person is a crucial document that is mandatorily required for the issue of a legal heir certificate either by the Municipal Authority or to apply for a...
question iconPOA from SriLanka to India citizen Resident Indian
Dear client, If the seller of the property is not now in India, he can still execute a POA abroad, but the process is slightly different. His first step is to visit the Indian Embassy or Consulate in...
question iconDarkast agriculture land sale
Dear Sir, If there is perpetual restraint from selling the land then the grandson cannot sell without the permission from the Deputy Commissioner. The conditions in the Darkasth to be read.
question iconMutation of property in authority records based upon registered gift deed
Dear Sir, Yes, the mutation will be taken place as jointly in respect of your respective wives. You have to produce certified copies of both the Gift Deeds.